

Projects under Construction
TO VIEW INTERACTIVE PROJECT MAP CLICK HERE
ST 15-01A FREEPORT PARKWAY, (BETHEL RD TO I-635)
The design contract for Freeport Parkway improvements was completed by J. Volk Consulting for a total contract amount of $726,000. The project includes full pavement replacement, bridge reconstruction, utility replacement / rehabilitation, landscaping enhancement, geometry improvements, trail construction, lighting, and a new traffic signal. The construction project was awarded to Texas Sterling Construction Co. for a total contract amount of $16,519,808.64. Construction is anticipated to begin in Spring 2018.
Latest Update:
Texas Sterling Construction Co. continues the water line replacement in Southwestern Blvd. The Phase 2 Utility work is approximately 95% complete. Paving repairs on Southwestern will begin once the utility work is complete. Franchise utility relocations are nearing completion, once completed the paving work on the Northbound lanes of Freeport will resume. Northbound lane bridge work is in progress.
Traffic on Freeport Parkway from W. Bethel to Dividend was reduced to one lane on the west side of the roadway.
These lane closures will be in place for the duration of the Freeport Parkway Rehabilitation project, which is expected to take 18-24 months. The expected completion date for the project is Spring 2020.
If you have questions or concerns about the project, please contact Kent Collins, P.E., Director of Public Works at 972-304-7019 or email kcollins@coppelltx.govTAX 2017A NEIGHBORHOOD ALLEY REPLACEMENT PROJECT #4
Selected neighborhood alleyways were chosen to be reconstructed based on pavement study results. Impacted alleyways are associated with Cambria Drive North & South, Woodhurst Drive South, Clear Haven-Still Forest and Tara Court. Construction is scheduled to start in late summer 2018 and is anticipated to be complete in late spring 2019. This project was awarded to Indus Road and Bridge, Inc. in the amount of $896,564.00. Caution should be exercised by anyone travelling within the alley construction zone.
If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-462-5151 or email jbrierton@coppelltx.gov
PROJECTS IN DESIGN
TAX 2015B PLANTATION DRIVE AND MOSSY OAKS STREET RECONSTRUCTION PROJECT
The design for these improvements is currently underway with Pape-Dawson Engineers. The project will impact the entire length of Plantation Drive and Mossy Oaks Street. The project includes complete pavement reconstruction and utility upgrades. Construction is anticipated in FY 2020-2021.
If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-462-5151 or email jbrierton@coppelltx.gov
TAX 2016B AIRLINE DRIVE
A design contract for the reconstruction of Airline Drive was awarded to Kimley-Horn in summer 2017. The project consists of concrete replacement, utility upgrades and sidewalk improvements. The project will also improve drainage. Construction is anticipated to begin in 2019.
If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-462-5151 or email jbrierton@coppelltx.gov
ST 16-01A/B S BELT LINE ROAD
A design contract for the reconstruction of S. Belt Line Road from Denton Tap Road to I-635 was awarded to Halff Associates, Inc. in the Spring of 2019. The project consists of paving, drainage, and utility improvements.
If you have questions or concerns about the project, please contact Kent Collins, P.E., Director of Public Works at 972-304-7019 or email kcollins@coppelltx.gov
TAX 2017B OAK GROVE LANEIf you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-462-5151 or email jbrierton@coppelltx.gov
If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-462-5151 or email jbrierton@coppelltx.gov
SOUTHWESTERN