​​​​​​​​​​​​​​​​​​​​​​​​​​​Projects under Construction

​​​​TO VIEW INTERACTIVE PROJECT MAP CLICK HERE


TAX 2014A PARKWAY BOULEVARD

T​he design contract for the Parkway Boulevard improvements was awarded to J. Volk Consultants, Inc. in August 2015. The project consists of removal and replacement of pavement, water, and sewer lines from Heartz Road to Lodge Road. The project will include an 8' sidepath/trail on the north side of the road from Heartz Road to Moore Road and a 6' sidewalk along the south side of the roadway. The construction project was awarded to Tiseo Paving Company for a total contract amount of $7,426,912.50​. Construction is anticipated to begin in Spring 2019.

Latest Update: 

The project is divided into several phases. Phase 1 of the project will begin on Monday, March 25, 2019, and work is expected to be completed in Spring 2020. Below are Tiseo Paving’s construction activities for Phase 1 of the project, which will occur over the next four to six weeks: 

1. Phase 1 of the project involves only the installation of utilities. 
2. Tiseo Paving will initially begin construction on the westbound lanes of Parkway Blvd from Heartz Road to Alex Drive/Parkway Place. Construction activities will include the installation of waterlines and storm sewers. No street paving will occur. 
3. Construction will happen one block (500 to 700 feet) at time. During this phase, Tiseo will fully close a section of the right, west-bound lane. Tiseo will also temporarily close the left, westbound lane from 9 a.m. to 3 p.m. each weekday. During these hours, traffic will be limited to a single lane in each direction on the eastbound side of Parkway Blvd Lane closures will be limited to only one block at a time. 
4. Tiseo Paving will stage construction equipment in the southeast side of Andy Brown Park East parking lot. This area will be fenced off for the protection of residents. 
5. During Phase 1 of the project, there will be no relocation of the mail boxes along Parkway Boulevard.​​

If you have any questions or concerns about the project, please contact: 
Kumar Gali, P.E., Assitant Director of Public Works - Engineering​ at 972-304-3679


ST 15-01A  FREEPORT PARKWAY, (BETHEL RD TO I-635)

The design contract for Freeport Parkway improvements was completed by J. Volk Consulting for a total contract amount of $726,000.  The project includes full pavement replacement, bridge reconstruction, utility replacement / rehabilitation, landscaping enhancement, geometry improvements, trail construction, lighting, and a new traffic signal. The construction project was awarded to Texas Sterling Construction Co. for a total contract amount of $16,519,808.64. Construction is anticipated to begin in Spring 2018.

Latest Update: ​

These lane closures will be in place for the duration of the Freeport Parkway Rehabilitation project, which is expected to take 18-24 months. The expected completion date for the project is Spring 2020.​

If you have questions or concerns about the project, please contact Kent Collins, P.E., Director of Public Works at 972-304-3679


PROJECTS IN DESIGN


TAX 2015B  PLANTATION DRIVE AND MOSSY OAKS STREET RECONSTRUCTION PROJECT 

The design for these improvements is currently underway with Pape-Dawson Engineers. The project will impact the entire length of Plantation Drive and Mossy Oaks Street. The project includes complete pavement reconstruction and utility upgrades. Construction is anticipated in FY 2020-2021.

If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-304-3679

TAX 2016B AIRLINE DRIVE 

A design contract for the reconstruction of Airline Drive was awarded to Kimley-Horn in summer 2017. The project consists of concrete replacement, utility upgrades and sidewalk improvements. The project will also improve drainage. Construction is anticipated to begin in 2020.

If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-304-3679

ST 16-01A S BELT LINE ROAD

A design contract for the reconstruction of S. Belt Line Road from Denton Tap Road to I-635 was awarded to Halff Associates, Inc. in the Spring of 2019. The project consists of paving, drainage, and utility improvements. Construction could start in the first half of 2021, pending funding availability.

If you have questions or concerns about the project, please contact Kent Collins, P.E., Director of Public Works at 972-304-3679

TAX 2017B OAK GROVE LANE
A design contract for the reconstruction of Oak Grove Lane was awarded to Pacheco Koch, LLC. in the Fall of 2018. The project consists of paving, drainage, sidewalk, and utility improvements. Construction is anticipated to begin in Winter of 2020.  

If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-304-3679

TAX 2017C CAMBRIA DRIVE AND WISE WAY
A design contract for the reconstruction of Cambria Drive and the Wise Way connection was awarded to Criado & Associates, Inc. in the Spring of 2019. The project consists of complete pavement reconstruction, utility upgrades, and storm drain improvements. Construction is anticipated to begin in 2021.​  

If you have any questions or concerns about the project, please contact Jamie Brierton, Project Manager at 972-304-3679​


FUTURE PROJECTS

SOUTHWESTERN BLVD
SPANISH MOSS AND JEB COURT​
NEIGHBORHOOD ALLEY REPLACEMENT PROJECT #5


Sidewalk repair process

1. DAMAGED SIDEWALK IS DEMOLISHED & REMOVED

2. GROUND IS COMPActED & PREPARED

3. WOOD FORMS ARE SET AND REBAR IS PLACED

4. CONCRETE IS POURED & CURES/DRIES TYPICALLY 24-72 HOURS

5. CONTROL JOINTS ARE SAWCUT AND SEALANT IS APPLIED TO EXPANSION JOINTS, IF ANY​